Construction
Construction of the Mary River project is
currently expected to commence during the summer of 2010, given
timely receipt of the necessary permits and approvals. It will be
staged from the future port site at Steensby Inlet, the existing
Mary River campsite, and several work camps situated along the
corridor of the future rail line. A construction access road will be
required between Steensby Inlet and the Mary River site to
facilitate rail line construction.
|
 |
Baffinland intends to seek permission to
pre-position equipment and materials to facilitate timely
construction. During the summer of 2009, dry cargo and heavy
equipment would be positioned near the beach at Steensby Inlet, and
fuel barges and barge mounted construction personnel camps would be
positioned offshore. Fuel, equipment and materials will also be
staged at Milne Inlet. As part of the pre-construction staging,
Baffinland would transfer materials and supplies from Milne Inlet to
the Mary River campsite using the existing winter road corridor.
Should the Mary River project not receive necessary regulatory
approvals to proceed to construction, pre-positioned equipment and
materials would be demobilized.
|