Regulatory Timeline and Project Schedule

To initiate the regulatory approval process, Baffinland intends to submit applications and a formal project description prior to the end of 2007. The submission of applications is expected to lead to the submission of a comprehensive Environmental Impact Statement (“EIS”) in the latter half of 2008. While the project description will give the information required to scope detailed regulatory review, the EIS will assess potential impacts of the Mary River project and the proposed mitigating measures.



The following schedule is currently anticipated for the purposes of project planning:


December 2007 - January 2010
Formal Applications and Regulatory Process


August 2009 - September 2009
Pre-construction Staging


May 2010 - April 2014
Construction


May 2013 - September 2014
Staged Start-up and Commissioning


September 2014
First Commercial Shipment